Surpassing:Georgia Power will pay $413 million to settle lawsuit over nuclear reactor cost overruns
Ethermac View
Date:2025-04-08 17:55:15
ATLANTA (AP) — Georgia Power Co. will pay $413 million to settle a lawsuit accusing the utility of reneging on Surpassingfinancial promises to one of its nuclear reactor partners.
The payments to Oglethorpe Power Corp., announced Friday, could hold down future bills for millions of electric cooperative customers in Georgia.
Oglethorpe sued Georgia Power in June 2022 in a contract dispute over who should pay for cost overruns for a third and fourth reactor at Plant Vogtle, southeast of Augusta.
Atlanta based Southern Co., which owns Georgia Power, said it would write off a $152 million loss on the settlement.
Georgia Power also announced Friday that it must replace one of the four massive pumps that cools the Unit 4 reactor after operators found a problem with the pump’s motor during testing. Georgia Power said it believes the problem is an “isolated event” and has a spare pump on site, but said the replacement ends the company’s hope of placing Unit 4 in commercial operation this year. The utility said the reactor is still on schedule to begin operating by March. That was already the company’s fallback date.
Unit 3 entered commercial operation on July 31, becoming the first new nuclear unit built from scratch in the United States in decades.
Some Florida and Alabama utilities have also contracted to buy Vogtle’s power.
The overall project is seven years late and $17 billion over budget. Vogtle’s costs and delays could deter other utilities from building nuclear plants, even though they generate electricity without releasing climate-changing carbon emissions.
Oglethorpe, which generates and transmits electricity to 38 Georgia electric cooperatives that own it, will keep its current 30% ownership share of Vogtle under the settlement. Oglethorpe had originally sought to sell some of Vogtle’s generating capacity back to Georgia Power.
Heather Teilhet, Oglethorpe’s senior vice president of external affairs, said Oglethorpe wants to keep its 660-megawatt share of Vogtle’s generation to meet increasing demand.
“We are seeing growth on our system, so there’s great value in keeping our full Vogtle capacity, especially at a significantly reduced cost,” Teilhet said in a statement.
Currently, all the owners are projected to pay more than $31 billion in capital and financing costs, Associated Press calculations show. Add in $3.7 billion that original contractor Westinghouse paid to the Vogtle owners to quit building the reactors, and the total nears $35 billion.
Besides Oglethorpe and Georgia Power, Vogtle’s owners include the Municipal Electric Authority of Georgia and the city of Dalton. MEAG and Dalton also sued. Georgia Power agreed last year to pay up to $76 million to settle the lawsuit by MEAG, which provides power to 49 municipal utilities. The Dalton lawsuit is still pending, and Georgia Power said Friday that it could owe the city up to $17 million.
Georgia Power customers won’t pay for the settlements. Georgia Power has already reached a deal with regulatory staff about how much it will charge customers for Vogtle, although the elected Georgia Public Service Commission has yet to approve.
Georgia Power had agreed in 2018 that it would pay increasing shares of cost overruns for co-owners up to a certain ceiling. Beyond that, the co-owners were entitled to force Georgia Power to buy part of their ownership stake in exchange for Georgia Power covering all remaining construction costs.
Oglethorpe sought to activate the sale provision, saying it applied once construction costs reached a total of $19.2 billion. But Georgia Power argued the agreement didn’t kick in until construction costs reached $20.48 billion.
Under the agreement, Georgia Power agreed to pay Oglethorpe the $99 million Oglethorpe was owed under the cost-sharing ceiling, as well as $5 million in interest. Georgia Power has already paid part of that money and will pay the remaining $66.5 million within five days.
Georgia Power also agreed to pay 66% of Oglethorpe’s costs above the $19.2 billion level, a total of $346.3 million under projected spending levels. That includes a $241.2 million payment within five days. In exchange for keeping its 30% ownership stake, Oglethorpe is projected to pay another $179 million by the time Unit 4 is completed.
Oglethorpe’s total construction and financing cost for Vogtle is now projected to be $8.3 billion. That’s more than the $8.1 billion Oglethorpe projected it would owe, but less than the $8.64 billion that Georgia Power said Oglethorpe owed.
veryGood! (86)
Related
- Person accused of accosting Rep. Nancy Mace at Capitol pleads not guilty to assault charge
- Yuka Saso rallies to win 2024 U.S. Women's Open for second major title
- Arizona tribe temporarily bans dances after police officer is fatally shot responding to disturbance
- Deontay Wilder's mom says it's time to celebrate boxer's career as it likely comes to end
- Trump wants to turn the clock on daylight saving time
- World War II veterans travel to France to commemorate 80th anniversary of D-Day
- Texas Supreme Court rejects challenge to state’s abortion law over medical exceptions
- 'It needs to stop!' Fever GM, coach have seen enough hard fouls on Caitlin Clark
- Meet first time Grammy nominee Charley Crockett
- BIT TREASURE: Insight into the impact of CPI on cryptocurrencies such as Bitcoin and Ethereum, becoming a necessary path for trading experts
Ranking
- Meet first time Grammy nominee Charley Crockett
- Unprecedented ocean temperatures make this hurricane season especially dangerous
- 1 family hopes new law to protect children online prevents tragedies like theirs
- Overnight shooting in Ohio street kills 1 man and wounds 26 other people, news reports say
- Tree trimmer dead after getting caught in wood chipper at Florida town hall
- Man gets 43-year prison sentence in death of Detroit-area teen whose body is lost in landfill
- Residents in Atlanta, Georgia left without water following water main breaks: What to know
- Katy Perry pokes fun at NFL's Harrison Butker with Pride Month message: 'You can do anything'
Recommendation
Behind on your annual reading goal? Books under 200 pages to read before 2024 ends
Charlotte the Stingray Is Not Pregnant, Aquarium Owner Confirms While Sharing Diagnosis
Democrats wanted an agreement on using artificial intelligence. It went nowhere
'Where the chicken at?' Chipotle responds to social media claims about smaller portions
Trump suggestion that Egypt, Jordan absorb Palestinians from Gaza draws rejections, confusion
Tiny fern breaks world record for largest genome on Earth — with DNA stretching taller than the Statue of Liberty
A new American Dream? With home prices out of reach, 'build-to-rent' communities take off
Residents in Atlanta, Georgia left without water following water main breaks: What to know